Milton House Main
Milton House Restoration Fund-Raiser Information

Construction Photos and Update

Memorial Tree
Calendar of Events
Historical Information
Visitor Information
Milton Historical Society Information

Related Links

Gift Shop
Scholarship Information
Contact Us

In spite of a year-long delay due to bureaucratic red tape, renovation and construction is well under way.  Due to this delay, there was a $400,000 shortfall to complete the project.  The Society went forward with the project as existing grants would have expired.

General contractor, J. P. Cullen & Sons, Inc., began demolition in the summer of 2004. Construction of the addition began in October.

Here are some photos of the project.

MVC-685F.JPG (417961 bytes)    Archeology began in 2003.  Corners of the former Goodrich block were excavated and cataloged as well as other excavations in selected areas that would be disturbed by the construction.  Over 10,000 artifacts were removed and cataloged by archeologist, Bob Fay.  Bob returned in 2004 when the construction began.  Another 10,000 artifacts were removed and are being cataloged.  Some of the items found were crockery, bottles, clay pipe stems, square nails, tableware, jewelry and window glass.   

MVC-110F.JPG (245507 bytes)    The larger cracks are being filled while lime mortar expert, John Speweik of U.S. Heritage Group is training workers to use lime mortar.

MVC-116F.JPG (310938 bytes)    June 2004--The scaffolding is up.

 

MVC-117F.JPG (340676 bytes)    The porch and outside stairway are removed from the Country Store.

MVC-670F.JPG (427296 bytes)    Masons repair damaged brick on the Country Store.

MVC-666F.JPG (394912 bytes)    The door that was at the top of the outside stairs that were removed has been bricked in.

MVC-153F.JPG (295183 bytes)    The 1980 finish is removed as well as any loose sub-layer.  Interesting facts about the construction were revealed.

P6290003.JPG (659255 bytes)    The seam you see in this photo tells a lot.  In fact, it changes what has been accepted about the construction of the building.  Up until now it was believed blocks one through five were built at the same time.  The section to the right of the seam is the north wall of block two.  You can see that there is a finish layer just to the right of the seam.  That indicates that the north wall of block two was once an outside wall.

P6290012.JPG (826652 bytes)    In this photo of the front wall of block one, you will notice definite horizontal layers.  These layers are contrary to the construction methods used in the hexagon.  This tells us  that this wall was not made of poured "grout" (lime mortar), rather it was layered with the "grout." 

The two facts listed above tell us that block one was probably built between the existing hexagon and block two after both were completed.

MVC-497F.JPG (254479 bytes)    Here you can see the outline of one of the original gables that crowned the top of the Milton House and Goodrich block prior to the 1867 addition of the third floor to the hexagon.

P7190003.JPG (743393 bytes)    Little by little the old is replaced with new.

MVC-718F.JPG (259112 bytes)    The exterior is completed.  

HPIM0148.JPG (1775718 bytes)    Excavation for the addition begins.

HPIM0159.JPG (1482554 bytes)    Excavation is temporarily halted when an old cistern is uncovered.

HPIM0430.JPG (1771822 bytes)    Some of the foundation walls are in.  The corner at the top left will remain open until the floor is laid to allow equipment access.

HPIM0723.JPG (1565716 bytes)    First floor concrete decking is in.

HPIM0806.JPG (970719 bytes)    New beams are installed in the cellar of the hexagon.

HPIM0812.JPG (1034254 bytes)    The inadequate electrical is brought up to code and fire alarm/suppression and heating systems are installed.

HPIM0838.JPG (1479618 bytes)    Interior walls must go in before the second floor decking is installed.

Picture 030.jpg (742829 bytes)    The pre-cast concrete exterior walls are delivered by truck . . .

Picture 039.jpg (738729 bytes)     . . . and hoisted into place.

P2220595.JPG (755489 bytes)    The process is repeated for the second floor.

Work will continue through the spring.  The original building will be available for tours as usual this spring and summer while work continues on the addition. 

The addition will be made watertight and secure but completion will be postponed until remaining funds are raised.

This is where you can help.  $125,000 is needed but any amount is welcome. 

This page sponsored by

Updated January 15, 2006